Kadaga,Roko Clash Over Slow Construction Of Parliament

Published on

- Advertisement -spot_img

Parliament is dissatisfied with the delays in the construction of the new Parliament Building, which was initially expected to be completed in July 2020.

ROKO Construction is constructing the Building located on Shimoni Road, and meant to reduce the congestion in the current facility and provide more space in the Chambers and offices.

Led by Speaker, Rebecca Kadaga, the leadership of Parliament toured the ongoing works only to find out that the contractor, ROKO has only completed three and a half of the nine levels.

Kadaga wondered why the contractor was employing a skeleton staff when work is way behind the schedule.

“On my way to office, I always peep in and I see only a handful staff; I advise you to consider night shifts, if you are to finish in the extra one year extension,” she said.

Parliamentary Commissioner, Francis Mwijukye, dismissed the contractor’s assertion that the delays were largely attributed to the Covid19 social distancing requirements, which forced them to reduce the number of workers.

“You cannot blame Covid19; many construction works have been going on well. If you are to finish this project in the next one year, you must not only work day and night but double the current efforts,” said Mwijukye.

The ROKO Project Engineer, Andy Sonnet, said he was not in position to guarantee having staff to work day and night since such arrangements would attract extra costs that were not included in the contract.

“We never priced for that, having staff who stay on site does not only require accommodation but also other items to ensure their safety and security,” said Sonnet.

Parliament’s Sergeant at Arms, Ahmed Kagoye, said Parliament is prepared to accommodate workers if ROKO would agree to night shifts.

Parliament’s leadership was appreciative of the several facilities that fall within the plan. The new building will host a chamber with the capacity to sit 600 MPs as opposed to the current one of 100 members. Other facilities include a museum, state of art archiving facility, gallery and increased space for offices.

The entire project is expected to be completed in July 2021.

Related

Ugandan Private Sector New Order Growth Sustained In July

Buoyant demand during July prompted firms to increase their purchasing activity and hire additional...

Big Size: All Set For Legendary Bebe Cool’s Break The Chains London Playback Event At Masq London Bar& Restaurant

Singer Bebe Cool kicked off his European leg of the Break the Chains media...

Uganda To Host 15th Brand Africa Awards, MTN CEO Sylvia Mulinge To Deliver Keynote Address

Uganda is set to be the centre of Africa's branding and marketing world...

Capt.Mukula Commences CEC Consultative Meetings In Soroti, Serere Districts

In a bid to secure another term on the National Resistance Movement's Central...

More from The Capital Times

Business Boom In Namugongo Ahead Of Martyrs Day

Business has picked up this morning at Namugongo Martyrs shrine according to traders. The...

Uganda Adopts Kiswahili As Official Language

Uganda has adopted Kiswahili as an official language, a top government official said on...

Minister Kasolo In Hot Soup Over Alleged Orungo Voter Attacks Accused Of Orchestrating Violence Fo Intimidate Opponents in NRM Primaries

A political storm is brewing in Orungo sub-county after shocking allegations emerged linking Uganda’s...