HomeBig StoryGovt Injects More Shs 781B Into Stalled Busega-Mpigi Expressway Project

Govt Injects More Shs 781B Into Stalled Busega-Mpigi Expressway Project

Published on

- Advertisement -spot_img

The Busega-Mpigi Expressway project works are expected to resume, following approval of a loan of Euros188.18 million (Shs781.04 billion) from the African Development Bank and Euros28.31 million (Shs117.46 billion) from the African Development Fund.

The loan, approved by Parliament during plenary sitting on Tuesday, 28 October 2025 is additional financing for the construction of the expanded 27-kilometre expressway.

The motion for the resolution of Parliament to approve the loan was moved by the Minister of State for Trade, Industry and Cooperatives (Industry), David Bahati.

Presenting the report of the Committee on National Economy, Deputy Chairperson, Hon. Robert Migadde, justified the additional financing, saying that government entered into an agreement with the contractor without adequate designs at an original cost of Shs547.5 billion which later increased to Shs1.35 trillion after the designs were submitted.

“In addition, the original project route alignment was re-aligned as the additional work items were considered integral to the functionality of the expressway as a toll road, resulting in an increased project scope of works,” said Migadde.

According to the committee’s report, additional financing was further required to cater for the increase of Project Affected Persons (PAPs) which was occasioned by the expansion of the project scope.

Migadde explained that the original PAPs were 2,885 but the re-alignment of the project route saw the number increase to 4,222 valued at over 167.7 billion.

“Out of the 4,222 approved Project Affected Persons, 2,585 have been paid valued at over Shs111.7 billion, leaving a total of 1,637 unpaid PAPs valued at over Shs5 billion,” said Migadde.

To mitigate further delays, the committee recommended that the works ministry should ensure that the contractor prioritises works in the unencumbered sections.

A minority report was, however, presented by Charles Tebandeke (Bbale County), also signed by Hon. Hassan Kirumira (NUP, Katikamu County South), wherein they urged lawmakers to stand-over the loan approval until the government chief valuer carries out a fresh valuation of compensation for all PAPs to ascertain the current costs.

Muhammad Muwanga Kivumbi (NUP, Butambala County) cautioned Parliament against approving the loan before ascertaining the exact funds required, saying that the project cost seemed exorbitant.

“What justification does government have to construct a kilometre at US$14 million. Parliament should move cautiously,” Muwanga Kivumbi said.

Kira Municipality Member of Parliament, Ibrahim Ssemujju, however, called for expeditious completion of the project, saying that the traffic on the Busega-Mpigi road is a nightmare.

“I am concerned that the Busega-Mpigi expressway has delayed and I will do anything to facilitate the completion of that road. I usually do not support loans but for this particular one, we need government to commit and the rest we shall investigate,” Ssemujju said.

Deputy Speaker, Thomas Tayebwa, said that completion of the project is crucial and urged the Minister of Works and Transport to give reassurance that the road works will connect to the Kampala-Entebbe Expressway, Ndeeba, Mityana and the Northern bypass.

The minister, Gen. Edward Katumba Wamala, said that the new design includes auxiliary roads, connecting to Mityana and Kasangi.

“There will be a complex interchange around Kyengera which will connect the Entebbe expressway, Mityana and Northern bypass. All this will be treated by the interchange and it is part if the reason we require additional funding,” Katumba Wamala said.

He added that the expanded works include four toll gates and bridges which were not considered in the original design.

“I want to say that we commit to address all the issues raised in the minority report and main report and I want to assure Parliament that the funds spent will be recovered because it is a toll road,” he said.

The Busega-Mpigi Expressway is multinational with Rwanda, Burundi and the Democratic Republic of Congo, whose works started in 2020.

Related

Court Throws Out Bail Plea For Bobi Wine’s Personal Guards, Kivumbi And Eddie Mutwe

The Kawempe Grade Two Magistrate’s Court has declined to grant a bail application submitted...

Police Launch Probe Into Death Of Woman At Bryan White’s Residence

Police in Kampala have launched investigations into the mysterious death of a 25-year-old woman,...

One People, One Destiny: Inside Museveni’s Bold Drive for East African Political Federation by 2031

Kampala — President Yoweri Kaguta Museveni has unveiled an ambitious regional integration agenda under...

The Obote- Bobi Wine Romance! Mutesa Rattling in His Grave But What Can Mengo do?

BY ANDREW BABA Bobi Wine’s homage to Obote is not just political theater—it’s a tragicomedy...

More from The Capital Times

Business Boom In Namugongo Ahead Of Martyrs Day

Business has picked up this morning at Namugongo Martyrs shrine according to traders. The...

Here is why the Faras Uganda is the Ultimate Convenience Mobility App for Every Ugandan

Kampala, Uganda – In a fast-paced world where time is increasingly precious, Ugandans are...

Museveni Inaugurates De Heus State Of The Art Fish Feed Factory In Njeru, Buikwe

Njeru, Jinja: De Heus Animal Nutrition, a global leader in animal feed solutions, has...