back to top
HomeBig StoryCharged MPs Roast Minister Gen Katumba Wamala Over Delayed Construction Of Katonga...

Charged MPs Roast Minister Gen Katumba Wamala Over Delayed Construction Of Katonga Bridge

Published on

- Advertisement -spot_img

The Minister for Works and Transport, Gen. Edward Katumba Wamala, has revealed that construction of a new bridge at the River Katonga along the Kampala-Masaka Highway will commence in October this year.

He made the revelation while responding to a matter of national importance raised by Kashari North County Member of Parliament, Hon. Basil Bataringaya.

Bataringaya expressed concern that repairs on the existing bridge had been abandoned and tasked the minister to give dates by which the key trade route would be fixed.
“Last year, the Katonga bridge was swept away and closed for more than six months. Temporary measures were taken to repair this bridge, and traffic was channeled through the long Sembabule road which was inconveniencing to traders in terms of money and time,” Bataringaya said.

He urged the works minister to create a shorter alternative route as works on the affected bridge take shape.
“And in this case, I propose the Villa Maria-Kalungu-Masaka Road,” he added.

Katumba Wamala said that the Katonga bridge was compromised due to meteorological changes which impacted the behaviour of the river.
“We had to study the meteorological behaviours of that river so that we can make a new structure which is resilient and will stand the test of time. We could not rush into establishing more or less the same bridge which had been compromised,” he said.

The minister also revealed that the contractor will address the challenges within Kalandazi and Lwera swamps to ensure that the section of the road is restored to meet the challenges of the truck volumes.

He also called on road users along the Kampala-Masaka Highway to exercise patience as construction works on the new bridge takes place.
“I want us to understand these structures are not simple structures to do. If we do a structure in a hurry, and it gives away in a few years, it will be this same House that will put us to task. This is a very sensitive structure and so it should be done with all the caution and detail it deserves,” said Katumba Wamala.

In May 2023, the Katonga bridge was destroyed by flash floods prompting the Government to create a diversion for heavy trucks to the Mpigi-Sembabule-Masaka Road.

 

 

Related

Christopher Ainembabazi Wins First Brand-New Car In Eyase Promotion

Kagwirawo is proud to announce Christopher Ainembabazi from Sheema, Western Uganda as the...

Marvelous: Shs 30M Up For School Fees As Always launches Girls Stay In School Campaign

In addition to producing the most reliable sanitary pads that provide all-round protection to...

Wow: Breathing New Life Into Government Communication

Uganda has made significant strides in service delivery, but too often these achievements remain...

How Security , URA Arrested Illegal Exporters of Battery Lead Scrap in Mukono

Acting on a specific intelligence, the Uganda Revenue Authority (URA)’s Customs department which is...

More from The Capital Times

Business Boom In Namugongo Ahead Of Martyrs Day

Business has picked up this morning at Namugongo Martyrs shrine according to traders. The...

Here is why the Faras Uganda is the Ultimate Convenience Mobility App for Every Ugandan

Kampala, Uganda – In a fast-paced world where time is increasingly precious, Ugandans are...

Museveni Inaugurates De Heus State Of The Art Fish Feed Factory In Njeru, Buikwe

Njeru, Jinja: De Heus Animal Nutrition, a global leader in animal feed solutions, has...