Parliament Approves Additional UGX 53 Billion For The Stalled Lubowa Specialized Hospital

Published on

- Advertisement -spot_img

Parliament has approved an additional UGX53.119 billion for the Lubowa International Hospital project, pushing the total government expenditure on the project to UGX529.588 billion. This decision comes after Prime Minister Robinah Nabbanja assured legislators that the hospital, whose completion has faced repeated delays, will be operational by April 2025. Nabbanja further revealed that medical personnel are currently undergoing specialized training in Italy in preparation for the hospital’s opening.

The approval, however, faced stiff opposition, with lawmakers raising concerns over limited access to the project site and a lack of transparency. Joel Ssenyonyi, chairperson of the Committee on Commissions, Statutory Authorities, and State Enterprises (COSASE), expressed frustration over Parliament’s inability to conduct on-site inspections. “The government keeps returning to Parliament for more funding, yet it denies us access to monitor progress. This raises serious questions about accountability,” Ssenyonyi remarked.

Despite the opposition, Nabbanja urged Parliament to release the funds, stating that construction is 61.8% complete, with most of the necessary medical equipment already procured. She emphasized that additional funding would ensure the hospital’s timely completion.

Deputy Speaker Thomas Tayebwa, who visited the site on two occasions, endorsed the funding, describing the progress as promising. He noted that over 700 workers are actively engaged in the project and expressed confidence in the contractor’s commitment to complete structural works by April 2025.

Concerns over accountability, however, remain a key issue. In a minority report, MP Ibrahim Ssemujju called for a halt to further disbursements until an independent audit is conducted. He cited a June 2023 Auditor General’s report that highlighted restricted access to engineers and inadequate supervision, warning of potential financial mismanagement.

Health Minister Dr. Ruth Aceng acknowledged challenges with oversight, revealing that construction progress stood at just 35% as of December 2024. She requested an additional UGX1.5 billion to bolster supervision efforts, admitting the absence of a consultant has left government engineers overstretched.

The debate underscores the divide between the government and opposition lawmakers over the handling of the Lubowa project, with demands for greater transparency continuing to dominate discussions.

Related

Three URA Officials Killed, Four Injured In Murchison Falls Crash After Vehicle Hits Elephant

Three officials from the Uganda Revenue Authority (URA) have died while four others sustained...

Queen Anisha Mugagga Signed as Mirinda Brand Ambassador for 2026 Mirinda Smiles Campaign

Uganda’s teen sensation and Miss High School 2025, Queen Anisha Mugagga, has officially been...

Kiromo Teenz Choice Awards 2026 Crowns Uganda’s Brightest Young Stars at UMA Show Grounds

The glamorous and highly anticipated Kiromo Teenz Choice Awards 2026 came to a thrilling...

Lawyer Ssebuliba Faces Mounting Financial And Legal Challenges

City lawyer Jordan Ssebuliba Kiwanuka is reportedly facing growing financial and legal difficulties, with...

More from The Capital Times

Business Boom In Namugongo Ahead Of Martyrs Day

Business has picked up this morning at Namugongo Martyrs shrine according to traders. The...

Here is why the Faras Uganda is the Ultimate Convenience Mobility App for Every Ugandan

Kampala, Uganda – In a fast-paced world where time is increasingly precious, Ugandans are...

Museveni Inaugurates De Heus State Of The Art Fish Feed Factory In Njeru, Buikwe

Njeru, Jinja: De Heus Animal Nutrition, a global leader in animal feed solutions, has...